UTP (Unshielded
Twisted
Pair)
Installation Guide
Transmission performance
criteria (Categories), have been established for the various grades of UTP
cables.
-
Category 5e – Specifies cable and connecting hardware with
transmission characteristics up to 100 MHz. It differs from Category 5 by
having 3 dB tighter NEXT requirements and additional requirements for PS NEXT,
ELFEXT, and PS ELFEXT.
-
Category 6 – Specifies cable and connecting
hardware with transmission characteristics up to 200 MHz. In addition Category
6 has tighter insertion loss, NEXT, PS NEXT, ELFEXT and PS ELFEXT over
Category 5e.
Cable HANDLING
Length
- The maximum horizontal
cable length is 90 meters (295 feet). 10 meters is allowed for cords in the
work area, and for patch cords or jumpers in the telecommunications closet.
- The maximum backbone
cable length of 90 meters (295 feet). This 90 meter length assumes that 5
meters (16 feet) are needed at each end for equipment cables connecting to the
backbone.
Pulling Tension
- Maximum pulling tension
for a 4 pair horizontal cable is 25 LBF. Excessive pulling tensions may occur
during installation. Once the damage is done, reversing the effect may not be
sufficient enough to correct the problem and cable replacement is recommended.
Intermediate cable pulls within the overall cable run may be necessary to
avoid exceeding the maximum pulling force.
Minimum Bend
Radius
- 4 pair UTP cables have
a 1” Min. Bend Radius
CAUTION:
Exceeding the minimum bend radius can distort the cable geometry and result in
degrading of transmission performance. Repositioning of the cable to the proper
bend radii may not correct the fault. Once the damage is done, the best option
is replacement of the damaged cable segment.
There are two common
places where exceeding the minimum bend may occur:
- At the work station
wall outlet. After the cable is terminated, too often the remaining cable is
jammed into the wall outlet, or worse, wrapped around itself and shoved into
the outlet. A better practice would be to gently work the excess cable length
back through the wall outlet into the wall.
- At the wiring closet.
During routing of the cable to the terminal block or patch panel. Prior cable
placement practices may have encouraged making the cable appear as formfitting
or tight against the routing structure (cable tray or rack) as possible. A
better practice would be to incorporate gently sweeping curves along the cable
path avoiding sharp bends or changes in direction. Every effort should be made
to ensure the path the cable follows has smooth gradual sweeps at any
transition point.
Over Stressing
Eliminate cable stress
caused by tension in suspended cable runs and tightly cinched cable bundles.
Excessive cable loading or
stress can also occur if a cable is incorrectly suspended in a cable run. A
recommended cable support spacing is 48" to 60" centers.
Avoid twisting of cable
during installation. Excessive twisting may result in distortion of cable
geometry, and in severe cases tears in the jacket.
In addition to the above
guidelines extracted from TIA/EIA-568, we strongly recommend the following
supplementary installation tips:
- Avoid walking or
stepping on high performance cable. Avoid running over high performance cable
with hand trucks or forklifts. This can exert excessive force on the cable
distorting cable geometry, or crushing the pairs resulting in electrical
shorts.
- Avoid the use of
tightly-fitting staples, either from a staple gun or mounting in a traditional
manner with a hammer. These can exert excessive force on the cable and distort
the pair geometry.
- D-Rings, nail on clamps
or Velcro straps all offer acceptable cable management techniques without
compressing the cable.
- Avoid cables run near
heat sources, as this may negatively impact cable attenuation.
- Maintain a 6" minimum
spacing between cables and sources of EMI such as fluorescent lights or
unshielded power lines.
Termination
Most modular jacks have the IDC connectors color coded for pair conductor
assignment to either 568A or 568B wiring methods. Pin pair assignments are
outlined for 568A and 568B. Maintain the same pin pair combination throughout
the installation. Changing pin pair assignment can result in crossed pairs;
consistency is the key. The modular jacks and cross-connect blocks employ IDC
connectors to complete the circuit between the cable and the hardware. A punch
down tool equipped with the appropriate blade (110 or 66) is recommended to
complete the termination and properly seat the conductor.
Terminate with connecting
hardware of the same category or higher. Any link which has substituted a lower
category component is automatically classified to that lower category.
The maximum allowable
amount of untwisting during cable termination to connecting hardware is 0.5" for
Category 5e and Category 6 cables. Exceeding the recommended length of
untwisting may cause performance problems. The same techniques should be
employed when terminating cross-connect blocks. Maintaining jacket integrity to
the point of termination aids in maintaining cable geometry and NEXT isolation
from adjacent cable pairs.
Bridged taps and splices
are not permitted as part of copper horizontal cabling requirements.
Adapted from material provided by
Mohawk Cable